Identification and Analysis of the Causes of Problems in the Implementation Stage of Construction Projects with APBD Funding Sources in West Sumatra Province

  • Yan Parta Wijaya Politeknik Negeri Padang, Indonesia
  • Oni Guspari Politeknik Negeri Padang, Indonesia
  • Suci Rahma Wijaya Politeknik Negeri Padang, Indonesia
  • Dewi Andriyani Politeknik Negeri Padang, Indonesia
Keywords: Construction Projects, APBD Fund Sources, West Sumatra Province

Abstract

Aims to determine and analyze the causes of problems that often arise at the implementation stage of construction projects with APBD funding sources in West Sumatra Province. The research method used is descriptive qualitative research, data collection through interviews, field observations and analysis of related documents. This research revealed several main causes of these problems, including a lack of thorough planning, frequent design changes, and problems in supervision and coordination between related parties. The results of this research can provide valuable insight for the West Sumatra Provincial Government in increasing the effectiveness of implementing construction projects with APBD funding sources. By understanding the causes of existing problems, corrective steps can be taken to optimize budget use and ensure the smooth running of construction projects. This research can also be a reference for construction researchers and practitioners in similar contexts in other fields.

Downloads

Download data is not yet available.

References

Agsarini, I. (2015). Pengaruh Faktor Internal Dan Eksternal Proyek Terhadap Kinerja Proyek Konstruksi Di Provinsi Kalimantan Selatan (Doctoral dissertation). Institut Technology Sepuluh Nopember.
Ali, A. A., & Fitrian, D. A. F. (2022). Jurnal: Kepastian Hukum Penerapan Asas Kebebasan Berkontrak Dalam Sebuah Perjanjian Baku Ditinjau Berdasarkan Pasal 1338 Kitab Undang-Undang Hukum Perdata. SENTRI: Jurnal Riset Ilmiah, 1(2), 270–278.
Cahyono, J. (2022). Analisis Yuridis Undang-Undang Nomor 2 Tahun 2017 tentang Jasa Konstruksi. Khazanah Multidisiplin, 3(1), 104–116.
Efrijal, F. T., Carlo, N., & Bakar, Y. (2014). Penilaian Risiko Biaya Kontrak Lumpsum dan Kontrak Unit Price Melalui Implementasi Metode AHP (Studi Kasus Kontraktor di Kab. Tanah Datar). Abstract of Undergraduate Research, Faculty of Post Graduate, Bung Hatta University, 4(3).
Ismaryadi, H., Khairani, K., & Mannas, Y. A. (2023). Implementasi Asas Itikad Baik Dalam Pemberian Kesempatan Penyelesaian Pekerjaan Pengadaan Barang Jasa Pemerintah. UNES Journal of Swara Justisia, 7(2), 680–694.
Jannah, M. P. N., & Musjtar, D. N. (2019). Penyelesaian Sengketa Wanprestasi Akibat Keterlambatan Pelaksanaan Perjanjian Kontsruksi Bangunan. UIR Law Review, 3(2), 41–49.
Kesek, R. A. E., & Hardjomuljadi, S. (2020). Analisis Red Clause Kontrak Konstruksi APBD Dengan Fidic Red Book 1999. Konstruksia, 11(2), 103–126.
Kombong, E. P., Nugroho, A. S. B., & Wibowo, R. A. (2020). Pelayanan Publik dan Kajian Putusan Korupsi Pengadaan Jasa Konstruksi dalam Perspektif Kontrak Jasa Konstruksi: Civil Engineering Perspective. Integritas: Jurnal Antikorupsi, 6(2), 245–262.
Labolo, M. (2017). Menutup celah korupsi pemerintahan daerah. Jurnal Ilmu Pemerintahan Widya Praja, 43(2), 93–110.
Maddepungeng, A., Bethary, R. T., & Chasanah, U. (2016). Analisis Perbandingan Risiko Biaya Konstruksi Antara Kontrak Lumpsum Dan Unit Price Menggunakan Metode Analytic Hierarchy Process (Ahp) Dan Decission Tree (Pohon Keputusan). Konstruksia, 8(1), 17–33.
Mahadiansar, M., Ikhsan, K., Sentanu, I. G. E. P. S., & Aspariyana, A. (2020). Paradigma pengembangan model pembangunan nasional Di Indonesia. Jurnal Ilmu Administrasi: Media Pengembangan Ilmu Dan Praktek Administrasi, 17(1), 77–92.
Martanti, A. Y. Y. (2019). Analisis faktor penyebab contract change order dan pengaruhnya terhadap kinerja kontraktor pada proyek konstruksi pemerintah. Rekayasa Sipil, 7(1), 32–42.
Ningrum, A. D. A. (2018). Penerapan Pasal 22 Undang-Undang Nomor 5 Tahun 1999 Tentang Larangan Praktik Monopoli dan Persaingan Usaha Tidak Sehat pada Tender Pengadaan Peralatan CT-Scan RSUD DR. Pirngadi Kota Medan (Studi Putusan KPPU Nomor 8 Tahun 2013).
Noumeiry, N. (2017). Kajian Faktor-Faktor Yang Berpengaruh Terhadap Kinerja Proyek Konstruksi. Jurnal Teknologi Berkelanjutan, 6(02), 110–117.
Nurtsani, R. A., Septiadi, D. R., & Suharyanto, S. (2017). Pengendalian Biaya Dan Waktu Proyek Dengan Metode Konsep Nilai Hasil (Earned Value). Jurnal Karya Teknik Sipil, 6(4), 460–470.
Ogunnusi, M., Omotayo, T., Hamma-Adama, M., Awuzie, B. O., & Egbelakin, T. (2021). Lessons learned from the impact of COVID-19 on the global construction industry. Journal of Engineering, Design and Technology, 20(1), 299–320.
Poerdyatmono, B. (2007). Alternatif penyelesaian sengketa jasa konstruksi. Jurnal Teknik Sipil, 8(1), 78–90.
Priyambodo, M. A. (2021). Mekanisme Penyelesaian Sengketa Konstruksi Menurut Undang-Undang Nomor 2 Tahun 2017 Tentang Jasa Konstruksi. Iblam Law Review, 1(3), 173–177.
Santoso, R. (2023). KINERJA INDUSTRI JASA KONSTRUKSI Suatu Tinjauan pada Lingkungan Bisnis dan Strategi Bisnis. Penerbit Tahta Media.
Sari, R. N. (2015). Pengaruh Pengawasan Inspektorat Dan Partisipasi Dalam Penyusunan Anggaran Terhadap Kinerja Manajerial SKPD (Studi Empiris Pada Instansi Pemerintah Kabupaten Tanah Datar). Jurnal Akuntansi, 3(1).
Soetanto, L. A., Setiobudi, K. J., & Nugraha, P. (2015). Analisa Kendala Pelaksanaan E-Procurement Di Kota Surabaya. Jurnal Dimensi Pratama Teknik Sipil, 4(2).
Sukwika, T. (2018). Peran pembangunan infrastruktur terhadap ketimpangan ekonomi antarwilayah di Indonesia. Jurnal Wilayah Dan Lingkungan, 6(2), 115–130.
Taurano, G. A., & Hardjomuljadi, S. (2013). Analisis faktor penyebab klaim pada proyek konstruksi yang menggunakan FIDIC conditions of contract for plant and design build. Konstruksia, 5(1).
Telaumbanua, F., & Syarif, Y. (2022). Proyek Pembangunan Gedung Menara Bank Bri Medan. Laporan Kerja Praktek Mahasiswa Teknik, 1(3).
Tumbel, S. M. (2017). Partisipasi masyarakat dalam pengelolaan dana desa di desa Tumaluntung Satu kecamatan Tareran kabupaten Minahasa Selatan. None, 6(1), 161029.
Published
2023-10-20
How to Cite
Parta Wijaya, Y., Guspari, O., Rahma Wijaya, S., & Andriyani, D. (2023). Identification and Analysis of the Causes of Problems in the Implementation Stage of Construction Projects with APBD Funding Sources in West Sumatra Province. JOELS: Journal of Election and Leadership , 4(2), 168-185. https://doi.org/10.31849/joels.v4i2.16288
Abstract viewed = 35 times
PDF downloaded = 20 times